Citywide Projects

UPDATE: 04/01/25- This project is still in the utility relocation phase. Utility providers will be on the right-of-way of both sides of Telephone Rd. moving their lines in preparation for the widening. There is no scheduled start time as it is dependent on the relocation efforts.

The project will consist of removal and replacement of sub-grade and base materials, as well as replacement of the existing driving surface with concrete between SW 19th Street and SW 34th Street.  Including necessary curb and guttering, storm drainage improvements, sidewalks, streetscape and utility line replacement.  Telephone Road will also be widened from 4-lanes to 5-lanes. This is a $10.9 million project. 

SW 19th st to SW 34th St

S. Santa Fe Street Repair
05/21/26- Oklahoma City crews will be starting concrete repairs in the area of 2900 S. Santa Fe starting May 26, 2026.  Santa Fe should remain open during the repairs with only one lane closing at a time.  The project is projected to take 2 weeks, weather permitting.
05/26/2026- Due to the weather this project has been delayed.  This project will not start until Thursday, May 28, 2026.

N Norman Ave
06/4/26 - New water rehab near the 1300-1400 block of N Norman.  Completion date TBD.

SE 34th St 
06/01/26 - New Sewer Rehab near the 300-600 block of SE 34th.  This project to be completed by July 1, 2026.  
Pole Rd
06/04/26 - Water Extention from NW 27th St along to Pole Rd to city limits.  This project to be completed by October 4, 2026.

Old Town Sewer Rehab
04/02/26 - Veolia will be working between Main St and SW 4th St, Telephone Rd to Broadway Ave on sewer rehab.  The project is projected to end in August 2026, weather permitting.

Excess dirt storage  
07/07/25- The City of Moore owns the property at 800 SW 4th St. Crews are currently storing dirt at this site from the SE 4th Street underpass project. This material will be used for future city projects.

Veterans Park: 
5/29/2026- Crews will be working on cleaning out a portion of the creek near SE 7th St. Bridge.  Work is set to begin by Mid-June 2026 with the competition date set for the end of June 2026, weather permitting. 

Buck Thomas Park Maintenance Yard Expansion: 
2/19/2026- Contractors will be working on expanding the maintenance yard at Buck Thomas Park.  Construction is set to begin the beginning of March 2026 with the completion date set for mid-June 2026, weather permitting. 

Buck Thomas Park Baseball Fields: 
2/6/2026- Contractors will be adding new restrooms at the Baseball Complex at Buck Thomas Park.  Work is set to begin by the end of January 2026, with a completion date set for the end of July 2026, weather permitting. 

Image
City of Moore Seal

Contact Us