Citywide Projects

UPDATE: 04/01/25- This project is still in the utility relocation phase. Utility providers will be on the right-of-way of both sides of Telephone Rd. moving their lines in preparation for the widening. There is no scheduled start time as it is dependent on the relocation efforts.

The project will consist of removal and replacement of sub-grade and base materials, as well as replacement of the existing driving surface with concrete between SW 19th Street and SW 34th Street.  Including necessary curb and guttering, storm drainage improvements, sidewalks, streetscape and utility line replacement.  Telephone Road will also be widened to from 4-lanes to 5-lanes. This is a $10.9 million project. 

SW 19th st to SW 34th St

07/23/2025 UPDATE:  Per the City of OKC, a piece of equipment broke down on Monday, delaying the completion of the eastbound lanes. This caused a ripple effect, requiring the traffic control company to reschedule.  The contractor is paving the eastbound lanes today and expects to finish by tomorrow, if not today. Traffic is scheduled to switch to the new lanes on Friday, going head-to-head. There is some work to be done on the westbound lanes on Friday. Paving of the westbound lanes is scheduled to begin on Monday and is expected to be completed by Tuesday, assuming no further delays.

07/18/2025 UPDATE: Per the City of OKC, the contractor on SW 149th expects to be finished next Friday, July 25th. All lanes will be open. There may be some traffic striping that needs to be completed, but temporary lane tags will be placed if the striping is not finished.

05/08/2025 UPDATE: Per the City of OKC, this project is currently set to be completed by the end of June. OKC has not accounted for all the weather delays in April, so it could run into July. They are hoping for a mid-July completion, weather permitting.

04/09/25 UPDATE: Per the City of OKC, SW 149th Street from Hudson Avenue to Vicki Drive will temporarily close to traffic from Friday, April 11, to Saturday, April 12. Crews are working on a storm sewer drain as part of the street widening project.

08/19/2024 UPDATE: Per the City of OKC, beginning Wednesday, August 21, 2024 Westmore Dr will be closed until May 2025.  The project construction manager has recognized potential safety concerns and has advised the City of Moore to close the street.

07/23/2024  Per the City of OKC, beginning Tuesday evening after 8:00pm, the Contractor performing the construction for the Widening of 149th Street in OKC from Santa Fe to Western will be closing lanes at the intersection of SW 19th St. and Santa Fe Ave. in Moore.  For Westbound traffic at the intersection, the existing left turn lane will be closed.  The existing westbound thru lane will be used for thru traffic as well as the left turn lane for traffic turning south during construction.  For Eastbound traffic at the intersection, the existing left turn lane will be closed.  The existing outside eastbound lane will be used for thru traffic as well as the left turn lane for traffic turning north.  The existing inside eastbound lane will now become the westbound lane for thru traffic.  Double yellow striping will separate the eastbound and westbound traffic west of the intersection during construction.  It is anticipated that construction will take approximately 8 months to complete.  Any questions regarding the project should be addressed with the OKC Project Construction Manager at 405-297-1768 or [email protected]

07/25/2025: 1824-1844 Sunrise Dr concrete planel replacement repair work.  Completion date will be 3 weeks, weather permitting.

07/22/2025: S Eastern Ave in front of Scooters Coffee-  Beginning July 25th, there will be storm pipe replacement and repair work in the right of way of S Eastern.  There will not be any street tear out on Eastern, but the right lane of Eastern will be closed. Completion will be approximately 2 weeks. 

07/25/2025: SE 4th & S Eastern- Painting of the signal light poles and mast arms.  There will be a bucket truck in the area, please use caution in the area.

07/17/2025: Between Norman and Arnold on NW 2nd St is still under construction.  Arnold St is completed except for the sidewalk.  The sidewalk will be completed in approximately 2 weeks, weather permitting.
07/25/2025:  This street portion of this project is completed.  They will be working on the sidewalks.

07/16/2025: Crews will start working on the south bound on ramp at SW 19th & I-35 for concrete panel repair.  One lane will always remain open; however, traffic may be slow.  This project should take about 2 weeks, weather permitting.
07/25/2025:  This project will be completed and open today.

07/14/2025: Pavement preservation treatment will begin July 14 in the following subdivisions: Broadmoore Heights, Prairie View, Seiter Farms, and The Waters.  Fore more information or to see a schedule for this project please visit Holbrook Asphalt

07/07/2025: Excess dirt storage.  The City of Moore owns the property at 800 SW 4th St. Crews are currently storing dirt at this site from the SE 4th Street underpass project. This material will be used for future city projects.

06/30/2025: Eastern & NE 4th St to Morgan Dr.- contractors for the City of Moore Water Department will begin moving in equipment for the installation of a new water main line. The installation will occur over the next few months, weather permitting. 

06/09/2025: SE 12th & S Eastern eastbound lanes on SE 12th Street will be closed for approximately 60 days to improve the grade change.  Eastern Ave will remain open during this project.
07/10/2025:  Construction is moving along as scheduled.  This project is set to be completed by the end of July, weather permitting.
07/25/2025: This project will be completed and open today.

03/15/2025- NW 24th, N. Janeway, Shields, and Vermeer- Crews will be installing new water main lines on NW 24th St, N. Janeway Ave & Vermeer Dr. This project is expected to be complete by the end of September 2025, weather permitting. 

Brand Senior Center:
07/18/2025- Crews will begin working on adding a handrail from the entry ramp of the sidewalk to the driveway.  Construction is set to begin by the beginning of August with the completion date set for mid August, weather permitting.

Little River Park:
06/26/2025- Crews will be working on adding a sidewalk from the parking lot directly to the front entrance of the Little River Splash Pad.  Construction is set to begin by the beginning August 2025 with the completion date set for mid-August, weather permitting.

Little River Park:
06/26/2025- Crews will be working on adding sidewalks from the New Exit Gates of the Little River Splash Pad to the existing sidewalks.  Construction is set to begin by the beginning of October 2025 with the completion date set for mid- October 2025, weather permitting.

Buck Thomas Park Softball Fields:
07/24/2025- Crews will be working on drainage issues for the softball fields.  Construction is set to begin at the beginning of November with a completion date set for the end of November 2025, weather permitting.

Buck Thomas Park Football Fields:
07/24/2025- Crews will be working on drainage issues for the football fields at Buck Thomas Park.  Construction is set to begin by the beginning of November 2025 with the completion date set for the end of November 2025, weather permitting. 

Urbansky Farms; nearest intersection is S.E. 19th & Sunnylane Rd.
Update: 06/12/2025- Property is being graded for development.

Cypress Creek; nearest intersection is S.E. 19th & Sunnylane Rd.
Update: 06/26/2025- Crews are installing sod and cleaning up and getting ready for final inspections.

Flicker Ridge; nearest intersection is N.E. 12th & Flicker Ridge.
Update: 06/12/2025- Crews are installing water and sewer improvements.

Broadmoore Heights; Section 3 nearest intersection is S.E. 34th & S Bryant Ave.
Update: 06/12/2025- Property is being graded for development.